Construction Home Loans: Progress Payment Stages, Valuations & Holding Costs
An Australian construction loan draws down progressively across five standard building stages (Slab, Frame, Lockup, Fixing, Practical Completion). Borrowers only pay interest on the cumulative drawn balance as each building stage is inspected and certified.
### The 5 Standard Progress Draw Stages
1. **Slab / Foundation Stage (15–20%):** Site levelling, pouring concrete foundation, drainage installation.
2. **Frame Stage (20%):** External wall timber/steel frames, roof trusses, window frames.
3. **Lockup Stage (20–25%):** Brickwork, external cladding, roofing, windows, and doors locked.
4. **Fixing Stage (20%):** Plasterboard, internal doors, cabinetry, electrical wiring, plumbing rough-in.
5. **Practical Completion / Handover (10–15%):** Painting, tiles, carpet, appliances, occupation certificate issued.
### Interest-Only During Build
During the 6 to 18-month construction period, the loan is strictly interest-only on drawn funds. Once practical completion occurs, the loan converts to standard principal and interest repayments.
Worked Calculation Examples
Holding Costs on a $400,000 Build at 6.00%
Interest charged across the stages of construction.
Stage 1 (Slab: $80k drawn): ~$400/month Stage 2 (Frame: $160k total drawn): ~$800/month Stage 3 (Lockup: $250k total drawn): ~$1,250/month Stage 4 (Fixing: $340k total drawn): ~$1,700/month Stage 5 (Handover: $400k fully drawn): Full P&I repayments begin.
Progress draws keep holding costs low while you are renting or paying another mortgage during the build.
Questions About Construction Home Loans: Progress Payment Stages, Valuations & Holding Costs
Direct answers to common borrower questions based on Australian credit guidelines and lender conventions.
Most Australian retail lenders refuse cost-plus contracts due to unlimited cost overrun risk. Lenders require a fixed-price contract from a licensed builder (e.g. standard HIA or Master Builders contract) with fixed progress stages.
Source: APRA Prudential Guidelines on Construction Risk
Lenders generally expect borrowers to fund builder variations and upgrades (e.g. upgraded stone bench tops or extra electrical points) with cash out-of-pocket, as increasing the approved loan amount during construction requires re-assessing credit.
Source: Housing Industry Association (HIA)
Related Tools & Reading
Primary Statutory & Regulatory Sources
- Building Contracts & Progress Payments Guide • Master Builders Australia (Verified: 2026-11-01)
- Consumer Protection in Residential Building • NSW Fair Trading (Verified: 2026-11-01)